Sample question 1 · Pmi
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
Correct answer:
A team charter lets the team agree on working hours, meeting arrangements, and how to revisit those agreements.
Sample question 2 · Pmi
A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.
What should the project manager do to avoid similar complaints?
Correct answer:
Confirm which decisions the committee makes and which information it needs. That provides a basis for tailoring the report's length and content.
Sample question 3 · Pmi
A project to implement a new online landing platform has started. After the first sprint, the project sponsor requested a change.
What should the project manager do next?
Correct answer:
The product owner and team can assess the proposed change, record it in the product backlog, and order it against other work.
Project Management Professional (PMP) is administered by Project Management Institute (PMI). Check the official PMP page (opens in a new tab) for current rules and registration.
People
Process
Business Environment
PMI sets the PMP passing standard with subject matter experts and does not publish a numeric cut score. Score reports show your performance in each domain as Above Target, Target, Below Target or Needs Improvement.
This page has 312 PMP practice questions covering the People, Process and Business Environment domains, including agile and hybrid scenarios. Weightings in the current 2026 Exam Content Outline differ from older material, so check that your study resources reflect it.
The PMP exam has 180 questions. 170 are scored and 10 are unscored pretest questions mixed in with the rest, so treat every question as if it counts.
Under the 2026 Exam Content Outline you have 240 minutes, with two 10-minute breaks. Once you take a break, you cannot return to the questions before it.
PMI does not publish a numeric passing score. Subject matter experts help PMI set the passing standard, and your report shows a performance rating for each domain.
PMI introduced a new Exam Content Outline in July 2026. Domain weights changed to People 33%, Process 41% and Business Environment 26%, the exam time is 240 minutes, and case-based and graphic-based questions were added.
You need 35 hours of project management training (or an active CAPM) and project experience gained in the last 10 years: 24 months with a degree from a PMI GAC-accredited program, 36 months with a bachelor's degree, 48 months with an associate-level degree, or 60 months with a secondary diploma. From December 1, 2026, live training counts only from PMI Authorized Training Partners, China Registered Education Providers or accredited academic programs.
PMP certification runs on a three-year cycle. To renew, you earn 60 professional development units (PDUs) during the cycle and pay the renewal fee.